At this week’s Watertown Common Council meeting, an update was given on the Town Square project. Concrete paver installation has begun in the fountain area, as has topsoil placement. Site concrete has been poured; completing the work within the park. The remaining site concrete work is along the south end of Water Street. Coming up, landscape plantings, sod, and seeding work will soon be completed, along with site plumbing work for the bubbler and at the water meter vault. Electrical work is continuing. To watch the full Watertown Common Council meeting, visit https://www.youtube.com/watch?v=JWHtJ_wzRak.